Test your knowledge Closing a project Quiz Answer

Test your knowledge Closing a project Quiz Answer


Project Execution: Running the Project 

Practice Quiz Answer



Week 6
Practice Quiz 1
Test your knowledge: Closing a project



Question 1)

Which of the following criteria must be met in order to close a project? Select all that apply.


  • Project team members have started new positions
  • Key stakeholders have acknowledged and agreed that the project is complete 
  • Agreed-upon project management processes have been executed
  • Project work has been completed



Question 2)

Which type of projects should a project manager avoid getting involved in because it can negatively impact their team? Select all that apply.


  • Short-term projects
  • Abandoned projects 
  • Challenging projects
  • Never-ending projects



Question 3)

What type of project exists when an incomplete handoff results in a final deliverable that never reaches the customer?


  • Scope-protected project
  • Abandoned project 
  • Closed project
  • Never-ending project




Question 4)

What type of project exists when project deliverables and tasks cannot be completed?


  • Scope-protected project
  • Closed project
  • Abandoned project 
  • Never-ending project